Short answer
Yes. Utility work inside an NCDOT right-of-way needs an encroachment agreement before work starts. The city may also need its own right-of-way or cut permit after NCDOT approves.
Which permit comes first
Is the street maintained by NCDOT?
YesNCDOT permit first, then the city permit
NoCity right-of-way permit only
Steps
- Confirm the road is state-maintained.
- Prepare plans showing the cut, depth, bore or open cut, and the restoration detail.
- Add a traffic control plan for the lane or shoulder closure.
- Submit the encroachment agreement to the NCDOT district office.
- After NCDOT approval, file the city right-of-way permit if the city requires one.
- Schedule the restoration inspection when the work is done.