Restaurant build‑out to TCO and CO
Cary, NC · Tenant build-out contractor
Sample photo · Sample project. Details changed.
- days, start to permit
- 44
- rounds of comments
- 0
- agencies, in order
- 3
The problem
Inspections were being booked one at a time. Two failed for items that could have been checked the day before.
- Before us
- Inspections booked one at a time · two failed
- With us
- Issued with no comments · 44 days
What we did
Built one closeout list across every open permit and inspection.
Walked the space before each inspection with the superintendent.
Sequenced the fire and utility sign-offs ahead of the TCO request.
Requested the TCO, then cleared the remaining items for the final CO.
Agencies, in order
- Town of Carybuilding inspections
- Town of Caryfire inspection
- Town of Caryutilities (grease interceptor)
Outcome
TCO issued 16 days after we started; the restaurant opened on its planned date. Final CO followed four weeks later.
Walking the space the day before every inspection, and doing the sign-offs in the order the TCO needs them.
Documents in the package
- Closeout tracker
- Inspection readiness checklists
- TCO request