Six-week lane closure for a mid‑rise build
Charlotte, NC · General contractor
Sample photo · Sample project. Details changed.
- days, start to permit
- 53
- rounds of comments
- 0
- agencies, in order
- 1
The problem
The schedule depended on the closure. The first traffic control plan did not show the pedestrian route, so the start date was at risk.
- Before us
- Traffic plan without a pedestrian route · start date at risk
- With us
- Issued with no comments · 53 days
What we did
Agreed the closure, the walkway and the delivery hours with the contractor.
Had our licensed partner update the traffic control plan with the pedestrian route and signs.
Filed the right-of-way use permit with the duration and phasing.
Set reminders for the extension request before the closure ran out.
Agencies, in order
- City of Charlotteright-of-way use permit
Outcome
Closure permit issued 14 days after filing; the crane started on the planned date.
Showing the pedestrian route up front, and asking for the extension before it was needed.
Documents in the package
- Traffic control plan with pedestrian route
- Phasing and delivery schedule
- Certificate of insurance