Water and sewer for 18 townhomes
Charlotte, NC · Residential developer
Sample photo · Sample project. Details changed.
- days, start to permit
- 42
- rounds of comments
- 1
- agencies, in order
- 2
The problem
The utility and right-of-way packages had been filed separately with different work dates.
What we did
Lined up the utility and right-of-way packages on one schedule.
Had our licensed partner add an overnight plating plan to the traffic control plan.
Answered one utility comment on the cleanout locations.
Agencies, in order
- Charlotte Waterservice connections
- City of Charlotteright-of-way permit
Outcome
Both permits issued the same week, 42 days after we started.
One schedule for two agencies, so neither waited on the other.
Documents in the package
- Utility service plan
- Traffic control and plating plan
- Comment response letter