Sidewalk replacement on a South Florida street lined with palms

Sidewalk and curb replacement along a commercial frontage

Fort Lauderdale, FL · Site contractor

Sample photo · Sample project. Details changed.

days, start to permit
50
rounds of comments
0
agencies, in order
1

The problem

The contractor works mostly in North Carolina and did not know the city's right-of-way submittal format.

What we did

  1. Assembled the package in the city's format; our licensed partner prepared the ramp details.

  2. Had our licensed partner add the pedestrian detour plan.

  3. Our local partner handled the site visits and inspections.

Agencies, in order

  1. City of Fort Lauderdaleright-of-way permit

Outcome

Permit issued 25 days after filing; final inspection passed the first time.

Knowing the format the city expects, and a local partner on site.

Documents in the package

  • Right-of-way permit application
  • Curb ramp details
  • Pedestrian detour plan