New commercial driveway on a state road
Raleigh, NC · Commercial developer
Sample photo · Sample project. Details changed.
- days, start to permit
- 65
- rounds of comments
- 1
- agencies, in order
- 2
The problem
The client had filed with the City first. The package came back twice: the City asked for the NCDOT approval, and the traffic control plan did not match the lane being closed.
- Before us
- Filed with the City first · returned twice
- With us
- Issued after 1 round · 65 days
What we did
Confirmed that US-70 is state-maintained and that NCDOT reviews the driveway first.
Had our licensed partner revise the site plan with sight distance, driveway width and radii called out.
Had our licensed partner redraw the traffic control plan for the actual lane and work hours.
Filed the NCDOT driveway permit, then the City right-of-way permit with the NCDOT approval attached.
Answered one City comment on the sidewalk detail and scheduled the inspections.
Agencies, in order
- NCDOTdriveway permit
- City of Raleighright-of-way permit
Outcome
City permit issued after one round of comments, 65 days after we started.
Filing in the right order. The City cannot finish its review without the NCDOT approval, so that came first.
We'd lost two months going back and forth. Once the order was right, it moved.
Documents in the package
- Site plan with driveway geometry
- Traffic control plan
- NCDOT driveway permit application
- Comment response letter