Stormwater and erosion control for a 40-lot subdivision
Wake County, NC · Residential developer
Sample photo · Sample project. Details changed.
- days, start to permit
- 67
- rounds of comments
- 1
- agencies, in order
- 3
The problem
Each review was moving on its own and two of them waited on each other.
What we did
Ran a pre-submittal audit of the plan set against each agency's checklist.
Set one schedule with the order each review needs.
Routed comments to the design professional of record and tracked responses.
Held a weekly status call with the developer.
Agencies, in order
- Wake Countyerosion and sedimentation control
- Wake Countystormwater review
- Town utilitieswater and sewer extension
Outcome
Land disturbance permit issued after one round of comments on each review.
One schedule for every agency, so no review sat waiting on another.
Documents in the package
- Audit report with missing items
- Review schedule
- Comment response tracker