Sidewalk replacement on a South Florida street lined with palms

Water and sewer connection in Broward County

Last verified November 8, 2026 · Reviewed by Sarah Johnson

Sample photo

Agencies
1
Typical weeks (sample)
4–10
Documents
4
Inspections
2
Last checked
November 8, 2026

Short answer

Yes. Connecting to county water or sewer needs a utility connection approval and the connection fees paid. Health department approval may also apply for new mains.

Agencies, in order

  1. Broward County: utility connection approval

Documents checklist

PreparedForYes1

  • Water and sewer availability letter request (the utility issues it)

You1

  • Contractor licence and insurance certificate

Licensed partner2

  • Utility plan with service sizes
  • Flow calculations for meter sizing

Steps

  1. Request availability for the property.
  2. Prepare the utility plan and flow calculations.
  3. File, answer comments and pay connection fees.
  4. Install, test and request meter set.

Inspections

  • Pressure and bacteriological test
  • Meter set

Fees, reviewer comments and sources

Fees
  • Connection feesSource: Broward County: water and wastewater services[$___]
Common reviewer comments
  • Availability letter has expired.
  • Backflow device is missing on the irrigation line.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.