Utility excavation permit in the Town of Cary right-of-way

Last verified November 11, 2026 · Reviewed by Sarah Johnson

Sample photo

Agencies
2
Typical weeks (sample)
4–10
Documents
5
Inspections
2
Last checked
November 11, 2026

Short answer

Yes. Digging in the Town of Cary right-of-way for utility work needs a right-of-way permit with a traffic control plan. On a state road such as NC 55, the NCDOT encroachment agreement comes first.

Agencies, in order

  1. NCDOT: encroachment agreementState road only
  2. Town of Cary: right-of-way permit

Documents checklist

PreparedForYes1

  • NCDOT encroachment agreement application and follow-up (state roads only; NCDOT decides)

You2

  • NC811 locate ticket
  • Contractor licence and insurance certificate

Licensed partner2

  • Utility plan with bore or open-cut method
  • Traffic control plan for work in the street

Steps

  1. Confirm who maintains the street and call NC811.
  2. On a state road, get the NCDOT encroachment agreement first.
  3. File the town right-of-way application with the traffic control plan.
  4. Notify the town before work starts and restore the surface.

Inspections

  • Backfill and compaction
  • Final surface restoration

Fees, reviewer comments and sources

Fees
  • Right-of-way permit feeSource: Town of Cary: right-of-way permits[$___]
Common reviewer comments
  • Bore pits are too close to the edge of pavement.
  • Work hours conflict with the school zone schedule.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.