Short answer

Yes. New or replaced sidewalk and curb cuts in the Town of Cary right-of-way need a town right-of-way permit. On a state road, the NCDOT driveway permit comes first.

Agencies, in order

  1. NCDOT: driveway permitState road only
  2. Town of Cary: right-of-way permit

Documents checklist

You1

  • Contractor licence and insurance certificate

Your design professional of record1

  • Site plan with sidewalk and curb cut dimensions

Licensed partner2

  • Accessible ramp detail
  • Traffic control plan for work in the street

Steps

  1. Confirm who maintains the street.
  2. On a state road, get the NCDOT driveway permit first.
  3. File the town application with the site plan and ramp detail.
  4. Receive the permit and schedule inspections.

Inspections

  • Forms before the pour
  • Final sidewalk and ramp

Fees, reviewer comments and sources

Fees
  • Town right-of-way permit feeSource: Town of Cary: right-of-way permits[$___]
Common reviewer comments
  • Ramp slope is not shown.
  • Detectable warning surface is missing at the ramp.
Sources