Short answer

Yes. Sidewalks, landscaping, signs, walls or other non-utility work inside a state road right-of-way need an NCDOT encroachment agreement. Get it before the city or county permit for the same work.

Agencies, in order

  1. NCDOT: non-utility encroachment agreementState road only
  2. City or county permit for the same work

Documents checklist

You2

  • Encroachment agreement form, signed by the owner
  • Maintenance responsibility statement

Licensed partner2

  • Plan showing the work inside the state right-of-way
  • Traffic control plan for work in the street

Steps

  1. Confirm the road is state-maintained and find the NCDOT district office.
  2. Prepare the plan and the encroachment agreement.
  3. Submit to the district, answer comments and get the agreement executed.
  4. Then file the city or county permit with the NCDOT approval attached.

Inspections

  • District inspection of the completed work

Fees, reviewer comments and sources

Fees
  • Encroachment review fee, where it appliesSource: NCDOT: driveway permits and encroachment agreements[$___]
Common reviewer comments
  • Wall is inside the clear zone; move it or add protection.
  • Owner signature is missing on the agreement.
Sources

Example content, not verified. Fees stay as [$___] until checked against the agency's current schedule.